09 Dec Remodeling Update: Phase 2
Progress update of the remodeling project at Primary Care Associates of Appleton
We are finishing up Week 5 of Phase 2 of the remodeling project. First and foremost, “Thank You” to all of our patients and visitors for your tolerance in navigating our corridors during this construction phase! Our goal is to make your trek throughout our facility as seamless as possible so please know ANY staff member you encounter is available to help you find your way.
With that being said, we have 5-weeks left of Phase 2 which tentatively takes us to a completion date of January 17th. IF everything stays on-schedule, we will be looking at our front desk area and patient entrance returning to the front of the building, as normal, on January 18th!
Items that have been accomplished over the past two weeks:
• Final portion of black top of front entrance/drive through area was completed
• Corridor walls being built where both men’s and women’s restrooms were previously located
• New section of front entrance framed out
• Enclosing of front entrance to begin exterior finishes on new, extended portion
• Ceiling tiles removed near West waiting area and corridor to current lab removed in order to frame out future continuous radius of area above front desk and walls
• Drywall, taping, finishing and painting of area near front desk and corridor.
We’ve received some very positive comments from our patients about the changes we are making to our front desk area and we are all looking forward to the new and improved PCAA facility!